DAILY NEWS Oct 28, 2009 5:00 PM - 0 comments

URANIUM DEVELOPMENT: Dewatering resumes at Cigar Lake

TEXT SIZE bigger text smaller text

SASKATCHEWANCameco Corp. of Saskatoon has resumed dewatering the Cigar Lake uranium project in the northern part of the province. Development was interrupted by an inflow of water on the 420-metre level that occurred on August. 12, 2008.

 

The leak has been plugged by remotely placing an inflatable seal between the shaft and the source. The area was then backfilled and sealed with concrete and grout. The company says the 420 level is not part of future mining plans.

 

Cameco expects dewatering the mine will take six to 12 months. An estimated production start date will be given after the water has been pumped out, the condition of the underground workings evaluated, remediation completed, and new development and production plans are in place.

 

The Cigar Lake development is a joint project of Cameco (50% and the operator), Areva Resources (37.1%), Idemitsu Uranium Exploration (7.875%) and Tepco Resources (5%). See www.Cameco.com for details.



Horizontal ruler
Horizontal Ruler

Post A Comment

Disclaimer
Note: By submitting your comments you acknowledge that Canadian Mining Journal has the right to reproduce, broadcast and publicize those comments or any part thereof in any manner whatsoever. Please note that due to the volume of e-mails we receive, not all comments will be published and those that are published will not be edited. However, all will be carefully read, considered and appreciated.

Your Name (this will appear with your post) *

Email Address (will not be published) *

Comments *



* mandatory fields