ONTARIO – Premier Gold Mines of Thunder Bay, ON, has filed a 43-101 compliant resource estimate for its Hardrock gold project. Although contained resources in the indicated category have grown 50%, overall inferred resources contain 27%...

ONTARIO – Premier Gold Mines of Thunder Bay, ON, has filed a 43-101 compliant resource estimate for its Hardrock gold project. Although contained resources in the indicated category have grown 50%, overall inferred resources contain 27% fewer contained ounces.

The indicated resource stands at 89.04 million tonnes grading 1.70 g/t Au and containing 4.87 million oz of gold. The inferred portion includes 23.15 million tonnes grading 3.69 g/t Au or 2.74 million contained oz. Both open pit and underground mining are planned.

The Hardrock deposit is the largest of four deposits near Geraldton that make up Premier's Trans-Canada property. The others are Key Lake, Bankfield West and Kailey. A feasibility study based on the Hardrock resources is due in the first half of 2015.

Please visit PremierGoldMines.com to view the latest corporate presentation.

Comments

Your email address will not be published. Required fields are marked *

Mar 27 2024 - Mar 28 2024
Mar 27 2024 - Mar 27 2024
Apr 08 2024 - Apr 09 2024
Apr 15 2024 - Apr 16 2024