ALBERTA - CANADIAN NATURAL RESOURCES (CNRL) of Calgary says that as of the end of September 2006, work was 47% comp...
ALBERTA - CANADIAN NATURAL RESOURCES (CNRL) of Calgary says that as of the end of September 2006, work was 47% complete on its Horizon oil sands project 70 km north of Fort McMurray. Capital spending has reached $3.26 billion, or 48% of the estimated $6.80 billion capital cost for Phase I development.

During the third quarter of 2006, CNRL said it awarded $400 million of contracts, bringing the contract total to $4.80 billion. Over 600 modules and oversized loads have reached the site, and more than half the modules have been installed. The major foundations have been completed; work has moved on to erecting steel, setting equipment and placing modules.

The Horizon project is to be commissioned during the third quarter of 2008.

The company's website, www.CNRL.com, includes an Opportunities button where contractors may register or view a list of the work available.

Comments

Your email address will not be published. Required fields are marked *

Apr 18 2024 - Apr 19 2024
Apr 23 2024 - Apr 23 2024
Apr 25 2024 - Apr 25 2024
May 06 2024 - May 07 2024