Agnico-Eagle suspends production during underground investigation

Agnico-Eagle Mines Limited has announced that it is suspending mining operations and gold production at its Goldex mine in Val d'Or, Quebec effective immediately.  This decision follows the receipt of an opinion from a second rock...

Agnico-Eagle Mines Limited has announced that it is suspending mining operations and gold production at its Goldex mine in Val d'Or, Quebec effective immediately.  This decision follows the receipt of an opinion from a second rock mechanics consulting firm which recommended that underground mining operations be halted until the situation is investigated further.

While the Company continues to assess the situation, it appears that a weak volcanic rock unit in the hangingwall of the Goldex deposit has failed.  This rock failure is thought to extend between the top of the deposit and surface.  As a result, this structure has allowed ground water to flow into the mine.  This water flow has likely contributed to further weakening and movement of the rock mass. 

"Considering the safety of the Company's employees, and the integrity of the mine's infrastructure and that of the surrounding area, the decision was made to stop production indefinitely" said Sean Boyd, Vice-Chairman and CEO.

It is estimated that the mill will continue to process feed from the remaining surface stockpile until the end of October.

The Company will assess the potential for restarting the mining operations next year on the western side of the deposit where the ore zone is narrower and still considered to be relatively stable, however, there is no guarantee that this will occur.  As a result, Agnico-Eagle will write off its investment in Goldex.  It is expected that this will total approximately $260 million (or approximately $170 million after tax, or $1.00 per share) and will occur in the third quarter 2011 financial results, scheduled for release on October 26.  Additionally, the Company expects to make an accounting provision for a portion of the anticipated costs of remediation in the third quarter of 2011.  All of the remaining 1.6 million ounces of proven and probable gold reserves1 at Goldex (approximately 10 years of mine life), other than the ore stockpiled on surface, will be reclassified as mineral resources.

Comments

Your email address will not be published. Required fields are marked *

Apr 18 2024 - Apr 19 2024
Apr 23 2024 - Apr 23 2024
Apr 25 2024 - Apr 25 2024
May 06 2024 - May 07 2024