Rosemont will cost more, Augusta says

Shares of Augusta Resource Corp. closed 7.8% lower at $1.66 per share following the release of an updated feasibility study that estimates higher capital and operating costs for its Rosemont copper project near Tucson, Arizona.

Shares of Augusta Resource Corp. closed 7.8% lower at $1.66 per share following the release of an updated feasibility study that estimates higher capital and operating costs for its Rosemont copper project near Tucson, Arizona.

Total initial capital costs for construction, commissioning and mine pre-development at Rosemont is estimated at US$1.2 billion, a 32% increase over the cost estimate in the company’s 2009 feasibility study.

The higher price tag reflects inflation across the industry for equipment, material and labour, the company noted, but also design changes Augusta Resource will make to meet the recommendations of the U.S. Forest Service.

Last year the USFS identified the barrel alternative as its preferred alternative, which is different than what the company had originally envisioned. The plan changes “respond to public and agency comments and include incorporating the latest agency requirements for impact avoidance, pollution control, habitat migration, resource conservation and public safety,” the company outlined in a press release.

Rosemont has also removed the processing of oxide ore from its mine plan and the capital associated with a heap leach and SX-EW plant.

John Hayes, a mining analyst at BMO Capital Markets in Toronto wrote in a brief research note that operating costs have climbed 43% from his previous estimate to US$8.89 per tonne, while the waste to ore ratio has fallen slightly to 1.9:1 from 2.0:1.

“Annual copper production is expected to average 243 million pounds over a 21-year mine life at a cash cost of US$1.02 per lb copper net of by-products,” he continued. “This compares to our estimate for 203 million lb copper annually over a 21-year mine life at a cash cost of US$0.67 per lb. A full analysis awaits publication of the full feasibility study; however, based on today’s update our 10% NAV could decline materially.”

The near surface, large tonnage, skarn-hosted, porphyry-intruded, copper-molybdenum deposit has updated reserves of 605 million tonnes grading 0.44% Cu for 5.19 million tonnes of contained copper and 0.015% Mo for 194 million lb of contained molybdenum.

Augusta Resource has traded within a 52-week range of $1.52-$4.95 per share. The company has about 143 million shares outstanding.

To read more Northern Miner articles, click here

Comments

Your email address will not be published. Required fields are marked *

Apr 18 2024 - Apr 19 2024
Apr 23 2024 - Apr 23 2024
Apr 25 2024 - Apr 25 2024
May 06 2024 - May 07 2024