Seabridge Gold’s (TSX: SEA) stock took a hit Thursday morning after B.C.’s Supreme Court quashed the KSM mine’s “substantially started” status. The ruling requires the province to reconsider the designation.
In 2024, the province’s assessment officer ruled the project had substantially started, meaning it would keep its environmental approvals despite ongoing Indigenous and environmental challenges to its development. But in June 2026, B.C.’s Supreme Court ruled the province had breached its constitutional duty by failing to properly consult the Tsetsaut Skii km Lax Ha Nation (TSKLH).
In a company news release, Seabridge confirmed the ruling but said the mine’s legal status has not changed.
“We are very confident that KSM has more than met the requirements for a substantially started designation,” said Rudy Fronk, Seabridge’s chair and CEO.
Meanwhile, Ryan Beaton, TSKLH’s legal counsel, says the decision affirms what the Nation has said for years, “that Seabridge and the province have been misinterpreting and downplaying the Court's original ruling in this case, creating confusion over the legal impacts of that ruling.”
The company’s shares closed at $25.92 on Thursday, down 29.26% from $36.64 the previous day, and fell another 4.32% on Friday to $24.80.
The stock regained 12.10% Monday morning in Toronto.
Located 65 km northwest of Stewart, B.C., KSM is one of the world's largest undeveloped gold projects, according to Seabridge. A 2022 preliminary feasibility study (PFS) estimated reserves totalling 47.3 million ounces of gold and 7.3 billion pounds of copper, with a net present value (NPV) of $7.9 billion (C$11.35 billion).
The news follows years of challenges to the mine’s development, with the TSKLH saying it was not properly consulted on the environmental risks the potential toxic waste from KSM’s tailings management facility (TMF) poses to waterways on its traditional territory.
Seabridge has previously taken issue with what it calls the assertion that the TMF is located on TSKLH’s exclusive territory. The company says Tahltan and the Nisga’a nations also have treaty rights in the region. In Seabridge’s statement, Fronk said KSM has “the full support of the principal First Nations who have recognized traditional territory and Treaty rights, respectively, in the area of KSM.”
In a written statement to the Canadian Mining Journal, TSKLH disputed Seabridge’s characterization of the Tahltan and Nisga’a as the principal First Nations in the area. The nation pointed to a 2021 ethnographic report on TSKLH Nation's rights and title claims and a 2023 letter from the provincial ministry of Indigenous relations and reconciliation, which it says supports its position that the land where KSM’s proposed TMF would be is part of Skii km Lax Ha's Awiijii territory.
The province must complete the required consultation and reconsider the designation. Seabridge says it will seek clarification on the timeline for a new determination.