Osisko Mining Corporation is pleased to report the successful completion of the installation of the second XL 2000 cone crusher at its flagship Canadian Malartic Mine. Installation and protocol testing were completed in the last half of July. Daily throughput rates at the Canadian Malartic mill averaged slightly above 46,800 tonnes per day over the last five days of July. Osisko President and CEO Sean Roosen said: “We have made good progress at Canadian Malartic in the past three months. The completion of the secondary crusher is an important moment in the move towards the end of the Canadian Malartic ramp up phase.”