BRITISH COLUMBIA – Construction at the Red Chris copper project 80 km south of Dease Lake is well underway, says owner Imperial Metals Corp. of Vancouver. Excavation in the process plant area has been completed, and the first concrete was poured near the end of September. The road between the plant area and tailings pond is complete. Plant start-up is planned in 2014.

The Red Chris mine will initially be two open pits and 30,000-t/d mill. Conventional truck and shovel methods will be used. Standard flotation technology is planned for the mill. Proven and probable reserves are 301.6 million tonnes at 0.359% Cu and 0.274 g/t Au. Over the life of the mine, 2.1 billion lb of copper and 1.3 million oz of gold will be recovered in concentrate.

Total direct costs of the project are estimated to be $320.8 million. Details are available in the 2012 Red Chris technical report.

See ImperialMetals.com.

Companies in This Story

Imperial Metals Corporation

Monitor These Topics


Horizontal ruler
Horizontal Ruler

Post A Comment

Disclaimer
Note: By submitting your comments you acknowledge that Canadian Mining Journal has the right to reproduce, broadcast and publicize those comments or any part thereof in any manner whatsoever. Please note that due to the volume of e-mails we receive, not all comments will be published and those that are published will not be edited. However, all will be carefully read, considered and appreciated.

Your Name (this will appear with your post) *

Email Address (will not be published) *

Comments *



* mandatory fields